Road Construction-Paving-COMPLETED 6/24/15

> News > Village News > Road Construction-Paving-COMPLETED 6/24/15

June 5, 2015

Effective Friday, June 12, 2015 through approximately Wednesday, June 23, 2015, the Department of Public Works will begin the process of paving the following streets:

  • Gould (Penora to Manitou)-Completed-6/12/2015
  • St. Mary's (Calumet to Village Line)-Completed-6/12/2015
  • Penora (Broadway to Terrace)-Completed-6/12/2015
  • Hawro (Penora to Calumet)-Completed 6/17/2015
  • Bloomfield (Broadway to Terrace)-Completed 6/17/2015
  • Lewan (French to the dead end)-Completed-6/18/2015
  • Intersection of French & George Urban-Completed-6/18/2015
  • Bonita (Alys Drive to the court on Bonita)-Completed-6/18/2015
  • Falcon (Warner to Village Line)-Completed-6/19/2015
  • Dorset (Ashford to Wayside)-Completed-6/19/2015
  • West (Broadway to Breck)-Completed-6/22/2015
  • Kieffer (Broadway to Dead End)-Completed-6/22/2015
  • Bellevue (Broadway to Terrace)-Completed-6/23/2015
  • Canton (Broadway to Terrace)-Completed-6/23/2015
  • N. Bryant (Gould to Terrace)-Completed-6/23/2015
  • S. Bryant (Broadway to Dead End)-Completed-6/24/2015
  • Bigelow (Broadway to Apple)-Completed-6/24/2015
  • Apple (Rutherford to Bigelow)-Completed-6/24/2015

Please note that all paving dates are tentative and weather dependent!

All residents need to be on the look out for road closings and parking restrictions.  Any questions, please contact the Department of Public Works at 716-683-5700.