Milling of Streets

> News > Village News > Milling of Streets

June 8, 2016

The Village of Depew is preparing to Mill and Pave the following Streets:

  • South Creek (from Dick to the Cul-de-sac). 
  • Candace (from Barnabas to George Urban)
  • Barnabas (from Helenbrook to Cardy)
  • Babbette (from George Urban to the Village Line)
  • Sherwood (from Burkhardt to George Urban)
  • Burkhardt (from Sherwood to the Dead End)

There are two processes to the project, the first part will start on or about June 9, 2016 and is a cold mill recycling where the top layer of the road is removed; the second process will begin a week or two later and is the replacement of the topcoat (paving). 

Village of Depew Department of Public Works staff will be on site through the entire process and will work with residents, bus drivers, etc, if access to the road is necessary.  During the milling process, residents will have access to their driveways, except for the short period that the milling machine is running in front of their homes. 

There will be no access to the streets on the day that we are topcoating (paving) your street.  We will have road barricades in place while the road is being paved and while it is hardening.  Access will resume once the barricades are removed.

During this entire process, we will be utilizing fire hydrants, which may disturb the main line and discolor the water, if this happens just turn on the cold water tap and let it run till is clears.

Thank you in advance for you cooperation and consideration.  If you have any questions, please contact Public Works at 716-683-5700.