Milling and Paving Season is now upon us!

> News > Village News > Milling and Paving Season is now upon us!

June 5, 2019

 

The Department of Public Works will begin Phase 1 of our Milling and Paving project.

No Parking signs will be placed in the affected areas.  Please adhere to the No Parking regulations of Monday through Friday from 6:30AM until 6:30PM to ensure that we can complete our work.

Phase 1 consists of the following streets:

A Street – Broadway to Terrace
Erie Avenue – Terrace to Gould
Bryant Avenue – Broadway to Terrace
Canton Street – Terrace to Gould
Easton Street – Litchfield to Westfield

Phase 1 will begin on or about June 13


Phase 2 consists of the following streets:

T.J.P. Court – Terrace to Litchfield
Preston Street – Terrace to South Dead End
Marengo Street – Terrace to Gould
Warsaw Street – Broadway to Gould
Calumet Street – Terrace to North Dead End
Neoga Street - Main Street to St. James

Phase 2 will begin on or about July 9